Developer told to pay RM11,800
for late delivery
01/11/2007 The Star
IPOH: A magistrate’s court here ordered a housing developer to pay RM11,800
to a housebuyer as compensation for the late delivery of his house in Sungai
Siput.
Magistrate Radzilawatee Abdul Rahman also instructed Ipoh View Sdn Bhd to
pay factory worker K. Davagee the sum with interests and costs.
On May 4, 2001, Davagee, 49, had signed a sale and purchase agreement with
Ipoh View to buy a double-storey terrace house in Taman Makmur for RM81,000.
According to the agreement, Ipoh View was to deliver the house within 24
months or pay Davagee an annual interest of 10% on the purchase price.
In Davagee's statement of claim, he said that the house should have
rightfully been delivered on or before May 3, 2003 but the certificate of
fitness (CF) for the property was only issued on Oct 13, 2004.
On March 10, 2006, Davagee issued a notice of demand for RM11,800 to the
developer for late delivery.
He subsequently sued Ipoh View when it failed to heed the demand later that
same year.
In its statement of defence, Ipoh View said vacant possession had been
delivered on June 9, 2004 according to the terms of the agreement.
It was only late by 386 days and not over 800 days as claimed by the
plaintiff, it added.
Ipoh View further claimed that vacant possession should not be calculated
from the date the CF was issued. |