Paradigm shift - CCC replaces
CFO
14/04/2007 The Star
The Certificate of Completion and Compliance (CCC) has replaced the
Certificate of Fitness (CFO) for Occupation to smoothen the delivery process
of building.
Under the new act, the architect or engineer of a project who submits
building plan is defined as the “principal submitting person” who will have
to issue the CCC before occupants can take ownership of their homes.
Previously, the power to check the technical aspects of a project and issue
the CFO was with the local authorities. (They will continue issuing CFOs for
projects where building plans were approved before the CCC date of
enforcement.)
The Housing and Local Government Ministry is mindful of the many problems
posed by the old system such as a delay in certification by technical
agencies, additional conditions imposed by the council at the time of CFO
application and lack of technical officers in the council to process the
CFO.
Under the CFO system
Under this system, the CFO is issued after:
the local authority receives the E form (UKBS) which is an application for
the issuance of a CFO
all conditions by the local authorities have been met
related technical agency certification has been received
the local authority has visited the site.
However, the existing law stipulates that a CFO is deemed issued 14 days
from the date the E form is verified as received by the local authority (PBT).
The law also allows registered building draughtsman (with the Architect
Board) to issue the CCC for buildings not exceeding two storeys high with
area less than 300m2.
CCC — a new system
The new system has the following characteristics:
IT is an extension of the existing CCC system for singly-built buildings to
buildings in other categories
THE CCC is issued by the Principal Submitting Person (PSP), who is a
professional architect, professional engineer or a registered building
draughtsman who submits building plans.
PLANNING permission and building plans should be approved by PBT beforehand
PBT is authorised to inspect the site at any time and to issue a notice if
there is a breach or divergence from the approved building plan
PBT can issue a notice in writing to a PSP to withhold a CCC issuance if the
breach or divergence is not rectified
PBT is allowed to execute rectifications considered necessary if the PSP
fails to do so
A RESPONSIBILITY process matrix is introduced. Each construction component
needs to be verified by professionals and contractors or trade contractors.
21 Form G will be inserted as a new schedule under UBBL 1984 (amendment)
2007
THE CCC will only be issued by the PSP after all parties are satisfied with
the supervision of the construction and that the building has been completed
according to the provisions of the laws and terms in the building plan
approval
Tightening the CCC system
To tighten the CCC system, amendments are made to relevant acts as follows:
STREET, Drainage and Building Act 1974 (Act 133)
i. A penalty for the offence of not abiding by the orders of PBT is
increased and imprisonment for a term not exceeding three years and a fine
of up to RM10,000 or
ii. General penalty increased iii. Substantive allocations regarding PSP’s
obligations are included, clearly including the penalty in the form of fine
and imprisonment if found guilty of an offence relating to the CCC
UNIFORM Building By-Laws 1984
i. Responsibilities in the matrix form are included through 21 new forms to
verify completion and compliance of each construction component
ii. The parties that issue the CCC without complying to the provisions of
the acts can be charged and reported to the controlling professional bodies
ENGINEER Registration Act 1967 (Act 138) and Architect Act 1967 (Act 117)
i. Stricter disciplinary actions on professionals by increasing fines,
extending the duration of membership suspension and cancellation of
membership registration
Roles and responsibilities of PBT
approving building plans
approving the planning permission application
conducting site inspections on own initiative or due to complaints
issuing a notice to PSP in the event of non-compliance with approved plans
and law
taking action to rectify any non-compliance by PSP if it considers such
works or measures are necessary
charging the PSP and professionals and reporting to the relevant
Professional Board for contravenes the Act
commanding that buildings that are higher than five storeys and are more
than 10 years old from the date when the CCC was issued, to be inspected for
safety level if necessary
The roles and responsibilities of PSP
SUBMITTING building plans to PBT for approval
COORDINATING plans other than the building plan to PBT before construction
operations at the site commence
SUPERVISING construction works at the site and ensure that the laws and
technical conditions of the PBT are abided by
REPORTING building breaches, explaining reasons for breach and stating
recovery actions in the event of a breach during construction
PRESENTING a work resumption notice to PBT
ENSURING non-compliance matters during construction as directed by PBT are
rectified before the CCC is issued
ISSUING the CCC to owners or developers, as well as a copy to PBT and
relevant Professional Board
ENSURING verification of all G forms are completed and in order and
presenting a copy of the G forms to the PBT and relevant Professional Board
The benefits of the CCC system
VACANT Possession (VP) can be issued together with the CCC. This can
overcome problems and implications that are associated with the CFO where
home buyers receive the house keys but cannot move in because the CFO has
not been issued
WITH the introduction of responsibility process in the matrix form, there is
an improvement in the accountability and transparency aspect where actions
can be taken on the responsible party in the event of failure or flaws in a
building, hence the work quality will be ensured
ONLY qualified and expert parties of a development will be given the
responsibility to certify the safety of a building which is the PSP.
Conclusion
For the purpose of CCC system’s standardisation and effective supervision, a
standardised enforcement date for all states has been set as April 12, 2007.
This system is consistent with the government’s desire to encourage a
self-regulation approach which was introduced in the new National Economy
Growth Planning strategy.
This effort reflects the government’s commitment to continuously enhancing
the service delivery system.
|